The data or status date represents the point in time to which the schedule reflects actual progress.
Evaluation of Options:
Option A: Incorrect. It’s not tied to monthly updates.
Option B: Incorrect. The status date is not when the project manager submits updates.
Option C: Incorrect. It’s not just a system-calculated date.
Option D: Correct. The status date reflects the date progress is measured.