AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 33 Topic 4 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 33 Topic 4 Discussion

PSP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

Each of the following accurately describes total float in a schedule EXCEPT:


A.

The amount of time an activity can be delayed without delaying the overall project completion time.


B.

Can be positive or negative.


C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.


D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.