Questions # 61:

Project Life Cycle Phases do NOT include the following item:

Options:

A.

procurement


B.

budgeting


C.

design


D.

start-up


Expert Solution
Questions # 62:

Which of the following will always describe the critical path? The path with

Options:

A.

The longest duration through the network.


B.

Zero float.


C.

Negative float.


D.

The shortest duration and negative float.


Expert Solution
Questions # 63:

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Options:

A.

Industry publications.


B.

Critical path schedules prepared by you for similar completed projects.


C.

The Petrochemical Industry New Plant Task Duration Handbook.


D.

The cost estimate for the plant prepared by your firm's estimating department.


Expert Solution
Questions # 64:

Budgeted cost of work scheduled is _______________________.

Options:

A.

The value of the completed work expressed in terms of the budget assigned to that work


B.

The total authorized budget for accomplishing the project scope


C.

The expected total cost of an activity, group of activities or the project


D.

The sum of all budgets for work scheduled to be accomplished within a given time period


Expert Solution