Questions # 51:

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

Options:

A.

Proceed with company processes even if they conflict with the client


B.

The client contract specifications always have priority


C.

Review any differences and negotiate workable specifications


D.

Suggest that the client issue a change order, accepting the contractor's processes


Expert Solution
Questions # 52:

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used


B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID


C.

Assigned party responsibility for each work task


D.

Tabular listing of activities showing duration, calendar ID, early and late dates


Expert Solution
Questions # 53:

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.


B.

Defining the execution plan to meet the required scope of work.


C.

Setting out the resource to be used and its limitations.


D.

Drawing the logic diagram.


Expert Solution
Questions # 54:

Why does activity 1001 have two successor activities?

Question # 54

Options:

A.

Because the late finish of 1001 and the late start of 7001 require two successors


B.

Because the problem could not effectively work with only one successor


C.

Because there are two defined logic paths for the work


D.

Because the duration of activities 2001, 2002 and 200.f require two successors


Expert Solution
Questions # 55:

The best source of project risk or opportunities is:

Options:

A.

A similar project in another state


B.

Rumors from the local Chamber of Commerce


C.

Failures by other contractors


D.

Internal and external stakeholders


Expert Solution
Questions # 56:

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

Question # 56

Options:

A.

80 lifts


B.

50 lifts


C.

5 lifts


D.

20 lifts


Expert Solution
Questions # 57:

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

Options:

A.

Avoiding a late delivery penalty from the owner


B.

Maximizing the $500,000 bonus


C.

Avoiding the 2023-2024 winter/wet weather season


D.

Minimizing the indirect expenditure chargeable to the contractor


Expert Solution
Questions # 58:

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:

A.

Delay due to SDOT's other projects


B.

Delay due to labor shortage


C.

Liquidated damages on the SDOT contract


D.

Cost overruns due to cement shortage


Expert Solution
Questions # 59:

When are KPIs defined?

Options:

A.

At project initiation


B.

At NTP


C.

At the start of the Construction Phase


D.

After the Bidding Phase


Expert Solution
Questions # 60:

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.


B.

Self-perform more of the work.


C.

Use a procurement agent to monitor and expedite equipment deliveries.


D.

Prepare better structural steel drawings.


Expert Solution