AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 55 Topic 6 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 55 Topic 6 Discussion

PSP Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

The best source of project risk or opportunities is:


A.

A similar project in another state


B.

Rumors from the local Chamber of Commerce


C.

Failures by other contractors


D.

Internal and external stakeholders