Question #: 56
Topic #: 6

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

PSP Question 56


A.

80 lifts


B.

50 lifts


C.

5 lifts


D.

20 lifts