PSP Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
Each column requires 2,000 cubic feet of concrete.
Lift Bucket Capacity:
Each lift bucket holds 40 cubic feet.
Calculate Number of Lifts per Column:
Number of Lifts = Volume of Concrete ÷ Bucket Capacity = 2,000 ÷ 40 = 80 lifts.
Cross-Verification:
Option B (50 lifts): Incorrect. Miscalculates required lifts.
Option C (5 lifts): Incorrect. Unrealistic for 2,000 cubic feet.
Option D (20 lifts): Incorrect. Underestimates.
Option A (80 lifts): Correct.