Crashing is a technique to reduce project duration by allocating additional resources to critical path activities. The most critical factor when crashing a schedule often pertains to external constraints that could severely disrupt progress.
Avoiding adverse weather conditions, such as the 2023-2024 winter/wet season, is paramount since such conditions can render activities impossible or highly inefficient.
The PSP Study Guide emphasizes that constraints, such as environmental conditions, play a pivotal role in project planning and execution. Managing these constraints effectively through schedule adjustments like crashing is critical to project success.
Financial incentives (bonus or penalties) and cost minimization, while important, typically take secondary priority when natural constraints risk derailing the project timeline entirely (PSP Guide, Section 1.2.4 – Project Variables and Constraints).
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit