Questions # 11:

What changes to logic would eliminate Activity B from the critical path?

Options:

A.

Replace the relationship from Activity B to Activity C with SSO


B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0


C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO


D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C


Expert Solution
Questions # 12:

As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?

Options:

A.

The Resource Breakdown Structure (RBS)


B.

The Work Breakdown Structure (WBS)


C.

The Organization Breakdown Structure (OBS)


D.

The Cost Breakdown Structure (CBS)


Expert Solution
Questions # 13:

: 20

Constraints control events or activities that __________________.

Options:

A.

Affect only the forward pass.


B.

Are not based on project relationships.


C.

Affect only the backward pass.


D.

May be over-ridden by activity logic.


Expert Solution
Questions # 14:

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

Options:

A.

The duration for drywall installation should De proportional to how critical the activity is


B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration


C.

Review the location of drywall work in the contract drawings


D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work


Expert Solution
Questions # 15:

Which of the following procedures is generally recognized as acceptable when updating a schedule?

Options:

A.

Report an actual date when the activity is on a non-work calendar for that date


B.

Change a previously reported actual date


C.

Change the WBS assignment for an activity


D.

Change a calculated date in the future


Expert Solution
Questions # 16:

Determine the correct formula and date for the late finish for Activity 9004.

Question # 16

Options:

A.

LS.10002 + 1 day -> 11-29-03.


B.

LS.10002^ Lag.7 + i day -> 11-20-03.


C.

LS.10002 - 1 day -> 11-27-03.


D.

LS.10002 - Lag.7 - l day -> 11-20-03.


Expert Solution
Questions # 17:

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.


B.

Periodic Windows.


C.

Collapsed As-Built.


D.

Time Impact.


Expert Solution
Questions # 18:

How many workdays occur from the start of the Product Testing to the Product Available milestone?

Options:

A.

70


B.

100


C.

60


D.

90


Expert Solution
Questions # 19:

What was the original planned duration for Activity A through Activity G?

Question # 19

Options:

A.

26.


B.

28.


C.

24.


D.

25.


Expert Solution
Questions # 20:

Should you verify the as-built schedule before proceeding with a schedule analysis?

Options:

A.

Yes, every dale needs to be verified but to not waste client money it should be restricted to just a few dates


B.

Yes. the accuracy of the analysis depends on the accuracy of the dates


C.

No. the contractor/owner dates should be reliable


D.

No the analysis should use the dates provided


Expert Solution