Should you verify the as-built schedule before proceeding with a schedule analysis?
Yes, every dale needs to be verified but to not waste client money it should be restricted to just a few dates
Yes. the accuracy of the analysis depends on the accuracy of the dates
No. the contractor/owner dates should be reliable
No the analysis should use the dates provided