AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 17 Topic 2 Discussion
PSP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
Option B: Incorrect. Packaging is not a direct predecessor of the product release.
Option D: Incorrect. Delaying manufacturing has no impact on proofing.
Option C: Correct. Expedites the critical path by compensating for the delay.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit