Industry-recognized methodologies for quantifying critical delays include:
Periodic Windows Analysis, which evaluates delays in defined time periods.
Collapsed As-Built Analysis, comparing completed work to a hypothetical as-built schedule without delays.
Time Impact Analysis, assessing the impact of delays based on scheduled activities.
A Gantt Chart (Option A) is a scheduling visualization tool, not a methodology for delay analysis. It lacks the analytical rigor and methodology required for critical delay quantification.