Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that


A.

It is calculated using the original logic.


B.

It is calculated using logic reflecting out-of-sequence progress.


C.

An out-of-sequence activity cannot resume until all predecessors are finished.


D.

There is no such thing.