Retaining existing logic means preserving the original relationships and dependencies defined in the schedule. Even if progress is recorded out of sequence, calculations adhere to the pre-established logic unless explicitly changed.
Option B reflects adjustments for out-of-sequence progress but contradicts the original logic requirement.
Option C imposes restrictions that do not align with typical CPM calculations.
Option D is incorrect as the concept exists.
The PSP Study Guide discusses the importance of maintaining logic integrity in CPM scheduling.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.