AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 16 Topic 2 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 16 Topic 2 Discussion

PSP Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

If Activity E's duration changes to 4 months, what is the overall duration of the project.

PSP Question 16


A.

19 months.


B.

20 months.


C.

22 months.


D.

21 months.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.