AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 15 Topic 2 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 15 Topic 2 Discussion

PSP Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

Which of the following procedures is generally recognized as acceptable when updating a schedule?


A.

Report an actual date when the activity is on a non-work calendar for that date


B.

Change a previously reported actual date


C.

Change the WBS assignment for an activity


D.

Change a calculated date in the future


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.