AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 14 Topic 2 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 14 Topic 2 Discussion

PSP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?


A.

The duration for drywall installation should De proportional to how critical the activity is


B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration


C.

Review the location of drywall work in the contract drawings


D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.