Activity 2004 (River Diversion to Pipeline) depends on completion of:
1001 (Preliminary Civil Work).
2001 (River Diversion Stage 1).
2002 (River Diversion Stage 2).
2003 (River Diversion Dam).
Exclusion of Other Activities:
Activity 2007 is not part of the crashed schedule's direct predecessor chain.
Other options include duplicated or incorrect entries.
PSP Study Guide Reference:Logical sequence analysis confirms these predecessors (Ref: PSP Study Guide, Chapter 2A: Activity Sequencing and Critical Path Analysis).