AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 14 Topic 2 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 14 Topic 2 Discussion

PSP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

PSP Question 14


A.

1001, 2001, 2002, 2003


B.

2001, 2002, 2003, 2007


C.

1001, 2002, 2003


D.

1001, 2002, 2002, 2003, 3001


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.