New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 12 Topic 2 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 12 Topic 2 Discussion

PSP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?


A.

The Resource Breakdown Structure (RBS)


B.

The Work Breakdown Structure (WBS)


C.

The Organization Breakdown Structure (OBS)


D.

The Cost Breakdown Structure (CBS)


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.