Which of the following is NOT input data to the construction planning process?
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
Under which circumstance should one perform resource-leveling calculations?
Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Which of the following phases does NOT describe the commonly accepted construction life cycle?
How many work days does it take to move the product from testing to sale?

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
What is accurate about Activity 7001 in the precedence diagram?
A driving relationship is _____________________.
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?