Construction planning relies on data from the owner, contractor, and contract terms to establish project parameters.
Bonding capacity is not typically part of the planning inputs but rather a procurement and contractual concern.
PSP Study Guide References:
Key inputs include project requirements, constraints, and stakeholder inputs as outlined in the PSP guide.
Conclusion: The correct answer is C, as bonding capacity is not a direct input to the construction planning process.