New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 41 Topic 5 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 41 Topic 5 Discussion

PSP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which of the following is NOT input data to the construction planning process?


A.

Input from the owner


B.

The contract


C.

Bonding capacity of subcontractors


D.

Input from the contractor


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.