AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 40 Topic 5 Discussion
PSP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
3 cranes working for 5 days = 3×30×53 \times 30 \times 53×30×5.
Total Lifts:
Total lifts = 450450450.
Verification with PSP Guidelines:
Efficient resource calculation is critical in equipment planning (Ref: PSP Study Guide, Chapter 2A: Resource Allocation and Optimization).