Option A: Incorrect. EF (Early Finish) is not needed for this calculation.
Option B: Incorrect. Uses LS and Dur incorrectly without connecting to LF.
Option C: Incorrect. Data provided is sufficient.
Option D: Correct. Matches both the formula and the date calculation.
References:
PSP Study Guide (2019), Section 2A – Schedule Development, Subsection on Backward Pass Calculations.
AACE Recommended Practices, RP 10S-90, discussing Late Start and Late Finish calculations.