The critical path determines the minimum project duration.
Path: A → B → G → H → 16 months.
Cross-Verification with Network Diagram:
Other paths have shorter durations or do not impact the overall project finish date.
Verification with PSP Guidelines:Critical path analysis is central to determining project duration (Ref: PSP Study Guide, Chapter 2A: Critical Path Method).