AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 39 Topic 4 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 39 Topic 4 Discussion

PSP Exam Topic 4 Question 39 Discussion:
Question #: 39
Topic #: 4

The project team must communicate the project plan, goals and objectives to all stakeholders to ensure the stakeholders understand the plan, goals and objectives and then continue this communication throughout the project life Which statement below would stakeholders NOT be expected to contribute?


A.

Stakeholders review the basis the schedule after the schedule is developed


B.

Stakeholder communication should be the single most Important objective of a program of key cost and schedule performance indicators (KPls)


C.

Early in the planning process, a set of well-defined goals and objectives is reviewed by the stakeholders


D.

The key to successful acceptance by all stakeholders is a set of well-defined goals and objectives which should be Identified early in the planning process


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.