Late Finish Analysis for Activity C (Develop Plans and Specs):
Activity C duration is 5 months, starting after Activity A (3 months).
Late finish = Early start of successor (Activity E) = 10 months.
Cross-Verification:
Based on backward pass calculations, Activity C must end by month 10 to not delay its successor.
Verification with PSP Guidelines:
Late finish values are calculated during backward pass (Ref: PSP Study Guide, Chapter 2A: Backward Pass and Float Calculations).