Incorporating realistic timeframes for shop drawing review and resubmittals in the baseline schedule prevents design-related delays.
Evaluation of Other Options:
A: Adding time buffers does not address the root cause.
C: Concurrent review may create confusion and errors.
D: Switching to post-tensioned concrete is a significant design change, not a practical solution for a scheduling issue.
Verification with PSP Guidelines:Adequate review time aligns with PSP scheduling best practices (Ref: PSP Study Guide, Chapter 2B: Schedule Development and Baseline Creation).