AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 37 Topic 4 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 37 Topic 4 Discussion

PSP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

What day would Activity C complete if the duration of Activity A was reduced by five days?


A.

35


B.

30


C.

45


D.

40


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.