AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 36 Topic 4 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 36 Topic 4 Discussion

PSP Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

Which of the following project planning situations is the most frequent contributor to cost overruns?


A.

lack of detailed planning for operational start-up


B.

Insufficient planning for change management


C.

Inappropriate definition of work breakdown structure


D.

Inadequate definition of scope at the estimate (budget) stage


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.