The Critical Path comprises the sequence of activities that directly impact the project’s completion time.
If only the last half of Activity B delays the subsequent activities, then this portion lies on the critical path.
References: PSP Study Guide, Section 2.4.3 – Schedule Analysis, emphasizes identifying segments of activities that are critical due to dependencies and float values.