PSP Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?


A.

Not suitable for complicated projects with multiple planned critical paths.


B.

Accuracy is increased by inserting delaying events into the as-planned schedule.


C.

Not suitable for projects with long durations.


D.

Less accurate as the analysis advances through the project.