Schedule updates track the current status of the project using actuals (start/finish dates), progress (percent complete), and future plans (remaining duration).
The original duration does not change and is part of baseline data, not required for routine updates.
PSP Study Guide References:
Scheduling update procedures are discussed, emphasizing active progress tracking elements like actual start, percent complete, and remaining duration.
Conclusion: The correct answer is D, as original duration is not a variable considered in regular updates.