AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 44 Topic 5 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 44 Topic 5 Discussion

PSP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Which of the following is NOT required when performing weekly or monthly schedule updates?


A.

Percent complete.


B.

Remaining duration of activities.


C.

Actual finish of activities.


D.

Original duration of activities.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.