Activity C (Develop Draft Plans and Specifications) has a duration of 5 months and is preceded by Activity A.
The diagram positions Activity C incorrectly since it starts simultaneously with Activity B, but Activity C should start after the completion of Activity A.
Cross-Verification:
Based on the dependencies, Activity C’s incorrect positioning violates the logical sequencing rule.
Verification with PSP Guidelines:Correct logic representation is critical for network diagrams (Ref: PSP Study Guide, Chapter 2A: Logical Sequencing).