AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 46 Topic 5 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 46 Topic 5 Discussion

PSP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?


A.

Projected crew size


B.

Estimated labor hours


C.

Hours in a standard work day


D.

Estimated cost


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.