When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
The critical factors are crew size, labor hours, and the standard workday.
Cost estimation is not directly required to calculate durations.
Evaluation of Options:
Option A: Incorrect. Crew size is needed for productivity estimation.
Option B: Incorrect. Labor hours are directly tied to durations.
Option C: Incorrect. Workday hours define the available time.
Option D: Correct. Cost is not directly linked to duration