AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 50 Topic 6 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 50 Topic 6 Discussion

PSP Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?


A.

Estimating remaining durations of activities.


B.

The correct recording of actual start dates.


C.

Making "downstream" logic revisions as required.


D.

Entering the time impacts of delays and change orders.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.