Accurate schedule updates rely on entering actual data (start/finish dates, durations) and evaluating impacts of changes.
"Downstream" logic revisions may be needed but are less critical compared to ensuring accurate historical data and reflecting immediate changes.
PSP Study Guide References:
Schedule updating emphasizes capturing accurate historical data and estimating remaining durations accurately.
Analysis of Options:
Option A and B: Key to progress tracking and forecasting.
Option D: Essential for reflecting impacts of delays and change orders.
Option C: While important, downstream logic revisions are less immediate compared to other procedures.
Conclusion: The correct answer is C, as downstream logic revisions are less critical in achieving an accurate schedule forecast compared to other updates