A driving relationship is the dependency link where the predecessor activity directly governs the dates of the successor activity.
Option A confuses "driving" with critical path relationships.
Option B oversimplifies by focusing on one type of relationship.
Option C is vague and does not specify the control aspect.
The driving relationship determines schedule flow and is essential for maintaining logical dependencies in CPM scheduling.