AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 52 Topic 6 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 52 Topic 6 Discussion

PSP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?


A.

Detailed listing of working days for each calendar used


B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID


C.

Assigned party responsibility for each work task


D.

Tabular listing of activities showing duration, calendar ID, early and late dates


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.