AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 51 Topic 6 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 51 Topic 6 Discussion

PSP Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?


A.

Proceed with company processes even if they conflict with the client


B.

The client contract specifications always have priority


C.

Review any differences and negotiate workable specifications


D.

Suggest that the client issue a change order, accepting the contractor's processes


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.