If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?
Proceed with company processes even if they conflict with the client
The client contract specifications always have priority
Review any differences and negotiate workable specifications
Suggest that the client issue a change order, accepting the contractor's processes