A procurement agent could monitor and expedite long-lead equipment, reducing delivery delays that often affect project timelines.
Evaluation of Other Options:
A: Hiring a senior project manager may not address the specific issue.
B: Self-performing may not resolve procurement delays.
D: Better structural steel drawings relate to design, not equipment delays.
Verification with PSP Guidelines:
PSP emphasizes early identification and mitigation of procurement risks (Ref: PSP Study Guide, Chapter 2B: Procurement and Supply Chain Management).