Question #: 64
Topic #: 7

Budgeted cost of work scheduled is _______________________.


A.

The value of the completed work expressed in terms of the budget assigned to that work


B.

The total authorized budget for accomplishing the project scope


C.

The expected total cost of an activity, group of activities or the project


D.

The sum of all budgets for work scheduled to be accomplished within a given time period