Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 3 Topic 1 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 3 Topic 1 Discussion

PSP Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?


A.

Subcontract outside forces to accelerate the Phase A Schedule


B.

Allocating forces from other BILCO contracts to the toll road project


C.

Proceeding with the work in advance of the environmental studies


D.

Reduce the phasing from 5 phases to 3 phases


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.