Late Start (LS) is calculated as LF−DurationLF - \text{Duration}LF−Duration.
For Activity 11001: LF−25=16Jan2024LF - 25 = 16 Jan 2024LF−25=16Jan2024.
Cross-Verification with PSP Guidelines:This formula aligns with the PSP methodology for backward pass calculations, where late start is directly computed from late finish and duration values (Ref: PSP Study Guide, Chapter 2A: Schedule Analysis).