Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 2 Topic 1 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 2 Topic 1 Discussion

PSP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?


A.

Using the critical chain method


B.

Fast tracking


C.

Crashing


D.

Rebaseline the project


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.