AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 1 Topic 1 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 1 Topic 1 Discussion

PSP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

PSP Question 1


A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.


B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.


C.

The activities occur in series with a 15-day lag.


D.

The activities run concurrently.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.