The use of a winter/wet weather seasonal calendar is essential in planning and scheduling to account for climatic conditions that can impact project timelines. The PSP Study Guide emphasizes identifying project variables, such as environmental conditions, and incorporating them into the project plan to manage risks and constraints effectively. Seasonal calendars help planners predict periods of reduced productivity, increased costs, and potential delays due to adverse weather conditions (PSP Study Guide, Subchapter 1.2.4, "Project Variables").
These calendars are particularly useful for:
Forecasting potential schedule impacts during specific periods.
Enhancing the accuracy of risk management plans (PSP Study Guide, Section 1.3.13, "Risk and Recovery Plan").
Aiding in decision-making regarding resource allocation during slow periods.