Free float is the time an activity can be delayed without delaying the start of its immediate successor.
Review Activity F in the Diagram:
Activity F has a successor that starts later, providing room for 2 months of free float.
Cross-Verification:
Option A: Incorrect. Overestimates the float.
Option B: Incorrect. No float is incorrect for F.
Option C: Incorrect. 1 month is insufficient.
Option D: Correct. Matches the calculated free float for Activity F.