Question #: 4
Topic #: 1

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using


A.

Finish-no-earlier constraint on the first activity


B.

Finish-no-earlier constraint on the last activity


C.

Finish-no-later constraint on the last activity


D.

Start-no-later constraint on the first activity