AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 7 Topic 1 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 7 Topic 1 Discussion

PSP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

What changes to logic would eliminate Activity B from the critical path?


A.

Replace the relationship from Activity B to Activity C with SSO


B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0


C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO


D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.