Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 7 Topic 1 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 7 Topic 1 Discussion

PSP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

What day would Activity C complete if the duration of Activity B was reduced to zero?


A.

50


B.

20


C.

30


D.

40


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.