To eliminate Activity B from the critical path, its dependencies must change so that its delay no longer impacts the path's completion time.
Replacing the A → B relationship with a Finish-to-Finish with Offset (FFO) and adding an FSO (Finish-to-Start with Offset) relationship from A → C allows Activity C to proceed independently of Activity B.
References: PSP Study Guide, Section 2.2.4 – Relationships and Calculations, explains how relationship types can influence critical path determination.