As of the data date/status date, the diagram shows progress beyond 5 days.
Review Actual Duration:
The progress bar indicates that 7 days have already been worked on Activity B.
Actual duration as of the status date = 7 days.
Cross-Verification:
Option B: Incorrect. Progress exceeds 3 days.
Option C: Incorrect. Progress is not 0 days.
Option D: Incorrect. Progress is more than 4 days.
Option A: Correct. Matches the observed progress on the diagram.
References:
PSP Study Guide (2019), Section on Network Diagrams and Status Updates.
AACE Recommended Practices, RP 10S-90.