Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.
Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.