Schedules primarily control time, cost, and resource allocations.
Quality management is related to design specifications and execution standards, not directly managed by schedules.
PSP Study Guide References:
The guide clarifies the limitations of scheduling tools in managing quality aspects.
Conclusion: The correct answer is A, as project schedules do not directly control quality.