Late finish (LF) is calculated by adding one day to the early finish (EF) of the final activity.
EF of Activity 11001 is given, and the late finish is simply EF+1EF + 1EF+1.
Cross-Verification with PSP Guidelines:
PSP methodologies state that late finish is derived from the forward pass using early finish logic, with specific adjustments based on activity relationships (Ref: PSP Study Guide, Chapter 2A: Forward and Backward Pass Calculations).