PSP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:


A.

Negative float.


B.

Free float.


C.

Total float.


D.

Interfering float.