Impact of Changing Activity E's Duration:
Activity E's new duration = 4 months.
The critical path passes through Activities A → C → D → E → H → I.
Recalculate Project Duration:
Original duration with E = 3 months: 19 months.
Increasing E to 4 months does not impact the overall path since it remains within the critical path's time allowance.
Overall project duration remains 19 months.
Cross-Verification:
Option B: Incorrect. Assumes additional delays.
Option C: Incorrect. Overestimates delays.
Option D: Incorrect. Miscalculates path changes.
Option A: Correct. Matches revised critical path duration.
[References:, PSP Study Guide (2019), Sections on Critical Path and Float Calculations., AACE Recommended Practices, RP 10S-90., , ]