AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 22 Topic 3 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 22 Topic 3 Discussion

PSP Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity


A.

Is a milestone.


B.

It is on the critical path.


C.

Was completed in the past.


D.

Has yet to be completed.