AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 26 Topic 3 Discussion
PSP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3
Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?
A WBS summary activity aggregates costs of constituent activities (2001 through 2004).
By summing the costs of activities as outlined in the schedule, the total cost for the WBS summary activity is calculated as $321,000.
References: PSP Study Guide, Section 1.3.7 – Establish Work Breakdown Structure, elaborates on cost consolidation at WBS levels.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit