To constrain a project's end date, a Finish-No-Later constraint is applied to the last activity. This ensures any slippage results in negative float, signaling delays relative to the fixed deadline.
Option A and B apply to earlier constraints, which are not relevant for controlling the project's end date.
Option D applies a constraint to the first activity, not the project finish.
This concept aligns with controlling project deadlines as described in the PSP Study Guide.