AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 26 Topic 3 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 26 Topic 3 Discussion

PSP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using


A.

Finish-no-earlier constraint on the first activity


B.

Finish-no-earlier constraint on the last activity


C.

Finish-no-later constraint on the last activity


D.

Start-no-later constraint on the first activity


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.