AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 26 Topic 3 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 26 Topic 3 Discussion

PSP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?


A.

$289.000


B.

$321.000


C.

$193,000


D.

$327,000


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.