If all other work proceeds according to the Baseline plan, how many times will the critical path change?
2.
1.
Does not change.
3.
Critical Path Analysis:
Critical path activities include proofing, printing, and packaging.
Delays or baseline adherence does not alter the sequence of critical activities.
Impact Assessment:
No additional changes occur to the baseline critical path in the given scenario.
Cross-Verification:
Option A: Incorrect. Assumes two path changes.
Option B: Incorrect. Incorrect number of changes.
Option D: Incorrect. Overestimates critical path shifts.
Option C: Correct. Reflects no critical path changes.