Determining the Late Finish (LF) of Activity 6002 involves analyzing its successor activity, 6003, and considering the lag (if any).
By subtracting 1 day from the Late Start (LS) of 6003, the Late Finish (LF) of 6002 is derived. The date calculation aligns with this logic, making 09 Mar 2023 the correct date.
References: PSP Study Guide, Section 2.2.5 – Constraints and Calendars, and Appendix A – Example CPM Problems, which detail LF and LS calculations.