AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 28 Topic 3 Discussion
PSP Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
A 5-day delay in product release impacts the printing window.
The printer is further delayed by 10 workdays.
Total Delay Impact Calculation:
The combined impact of the testing and printing delays = 5 + 10 = 15 days.
This results in a cumulative delay in product release.
Cross-Verification:
Option B: Incorrect. Ignores delays entirely.
Option C: Incorrect. Assumes only one source of delay.
Option D: Incorrect. Underestimates delay impact.
Option A: Correct. Matches the calculated total delay.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit