AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 25 Topic 3 Discussion

AACE International Planning & Scheduling Professional (PSP) Exam PSP Question # 25 Topic 3 Discussion

PSP Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?


A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.


B.

Replace the relationship from 'B’ to 'C’ with SSO


C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort