The Late Finish (LF) of Activity 7001, when compared with dependencies in the precedence diagram, does not align with logical flow, indicating an error in its calculation.
Validating LF involves backward pass calculations, which must respect lags and durations.
References: PSP Study Guide, Section 2.3.4 – Schedule Change Management, and 2.4.3 – Schedule Analysis, focus on identifying and correcting logic or calculation errors in schedules.